(     ) is the sum of all budgets established for the work to be performed.
A. CPI
B. BAC
C. SPI
D. EAC


相關試題

72題: The IoT architecture can be divided into three layers.  (     ) is the key layer to realize the foundational capabilities which support the electronic devices interact with physical world.
A. Sensing layer
B. Network layer
C. Application layer
D. Operation layer
答案解析與討論:www.urtiwb.tw/st/389204944.html

73題: Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups. (   ) process does not belong to Project Integration Management.
A. Developing project charter
B. Developing project management plan
C. Analyzing project risks
D.Monitoring and controlling project
答案解析與討論:www.urtiwb.tw/st/389212434.html

74題: In project management and systems engineering, (     ) is a deliverable-oriented breakdown of a project into smaller components. It is a key project deliverable that organizes the team's work into manageable sections.
A. RBS
B. PBS
C. GBS
D. WBS